Case Study – Education New Build
Minsthorpe Community College, Phase 2
Penetration sealing and intumescent fire stopping for a new sports facility in South Elmsall, delivered for HBC Construction.
Main Contractor
HBC Construction
Location
South Ellmsall, West Yorkshire
Package Value
£220k installation
Sector
New build education
Buildings
Sports hall, studios & changing rooms
Certification
IFCC certificated installer
Project Overview
Fire Stopping for a New School Sports Facility
HBC Construction appointed Elite Fire Stop Ltd to deliver the penetration sealing and intumescent fire-stopping works for Phase 2 at Minsthorpe Community College, a new sports facility built under the Department for Education’s School Rebuilding Programme.
Our works ran throughout the new building, including the sports hall, changing rooms and associated areas, maintaining the required fire resistance and compartmentation throughout.
Elite Fire Stop were professional, reliable and proactive throughout the project. Their communication and technical expertise made the process seamless, and the quality of their work was excellent. We wouldn’t hesitate to work with them again.
How We Delivered It
Challenge, Approach, Result
01
The Challenge
Air testing identified areas of air leakage that fell outside our original scope of works.
We responded quickly, carrying out high- level air-sealing works to fix the leaks and help the project reach its required air-test performance.
02
Our Approach
We engaged early with the wider project team so other trades understood the fire-stopping requirements.
Beams passing through fire-rated walls fall under a different test standard and can’t simply be fire-batt sealed, so they were capped and encased before our works began. Regular quality checks and open communication kept issues small and early.
03
The Result
-
Compliant installation without unnecessary rework or delays
-
Non-conformance issues prevented on site
-
Air-test performance supported with extra air sealing
-
Required fire resistance and compartmentation maintained
Scope of works
What We Installed
Penetration sealing throughout the new building Penetration sealing →
Sports hall, changing rooms and associated areas
Intumescent fire stopping Passive fire protection →
High-level air sealing following air testing